Westpark Electric Ltd. recently completed a major upgrade to Altalink s Winefred Lake substation. This site is located 150km southeast of Fort MacMurray, Alberta.

Work consisted of installing a new 25 MVA 138 x 25 kV transformer, buswork, and related control modifications to supplement local electricity supply for continuing heavy oil development in the area. The existing equipment was removed after commissioning of the new equipment was completed. Work was completed ahead of schedule.